Overview
Certain manufacturing processes are subject to partial yields by nature. It is common in chemicals and other process industries, and also
in those involving detailed manual labor work or high tech product
with quality standards such as medical device manufacture.
In a
process routing (or master recipe) where multiple operations/phases are
involved, the yield rate progressively depletes the pass through quantity and
final throughput.
For example:
Operation Start Quantity End Quantity Yield Rate
0010 100 90 90%
0020 90 72 80%
0030 72 72 100%
0040 72 72 100%
in this example, the overall throughput is 72 on a start quantity of 100, with the first two operations involving progressive yields of 90% and 80% which calculate on top of one another.
These scrap/yield rates are studied on floor and arrived at statistically by the work study/industrial engineering departments, typically.
The challenges at hand in setting this up in SAP:
1) How to plan for adequate order quantity to meet a given demand
2) How to plan for adequate capacity of different work centers involved
3) How to plan for components that are needed at different operations
4) How to estimate the cost accurately in this scenario
5) What happens when the reality on the shop floor differs from the estimates.
1) How to plan for adequate order quantity to meet a given demand
MRP order quantity for the product involving partial yield rates can be inflated by a parameter called "Assembly Scrap" in the MRP1 view of the SAP ERP and S/4 HANA. Going by the above example, 28 extra is needed for this order to make 72 which is computed as 38.88% assembly scrap. Note: In the traditional ERP product, SAP started with scrap as a percentage of final throughput (or yield) which they subsequently corrected in other products like APO and IBP. with this scrap parameter of 38.88% If a production order (or a planned order) is created with a target quantity of 72 EA, the start quantity will be inflated to 100. If a fixed lot size is set for the material, then it becomes default quantity to start, and the target quantity will be computed instead.
2) How to plan adequate capacity and scheduling of work centers
In order to indicate the progressively reducing throughput from one operation to next, the foillowing scrap rates need to be entered in to the routing at operation level:
operation1 - operation scrap 10%
operation2 - operation scrap 20%
Assuming each operation takes 1 hr to execute per piece, the resource capacity will be computed at 100 hr for 100 EA quantity of the order; whereas resource capacity of second operation will only need to be planned for 90hr in view of the reduced quantity by the time the order progresses to it. If there are more subsequent operations which have no further scrapping planned, they will be planned for a capacity to to meet 72 EA of the passthrough quantity that should result at that stage. Note: This setting (Routing operation scrap) can only influence the work center activity but not the component quantities in SAP.
3) How to plan for component requirements
Let us say this product needs two components, component1 in the first operation, component2 in the second operation, and perhaps another component3 in the 3rd or later operation.
For simplicity, let us assume are these components are needed 1:1
for the product being produced.
In the above example, we would need
100 EA of
component1 (to meet operation1 start quantity)
90 EA of component2 (to meet the
start quantity of opneration2 where it is needed).
72 EA of component3 (as by this operation, the throughput quantity stands reduced to this)
With the Assembly scrap described in (1) the order quantity will be inflated to 100 EA. As already discussed in (2) the routing operation scrap is not able to influence the component quantities. Therefore
If nothing else
is done, this has the effect of planning both components to the tune of 100 EA
to meet this order quantity.
This will result in the second and subsequent components being excess planned for this order. In order to finetune this, there are two different possible parameters at the BOM component level:
3.1) BOM operation scrap: when this parameter is filled in, the netID field must also be marked. The combined effect of these two fields will be to use the specified BOM Op Scrap% to override the assembly scrap% specified for the header.
In our example the following settings are recommended:
component1
(going to 1st operation) - no BOM Op scrap and no netID - therefore the header
assembly scrap% will be used to plan this component.
component2 (going to 2nd
operation) - enter BOM operation scrap of 20% with netID marked (just like
routing op scrap for that oper2) so that component2 is planned only for 20%
extra on the target 72 (which is 90 EA) rather than 38.88% extra (100 EA)
component3 (going to 3rd operation) - here no scrapping is intended, therefore
planning should happen only for target 72 EA. In this case - enter no value (or
zero) BOM operation scrap and mark the netID indicator.
3.2) Component scrap: This parameter is available at two levels - as part of BOM component attributes or as a general parameter at the material master level for the component. If both are entered, then the more specific BOM level value takes precedence
SAP gives more flexibility with this field when used within BOM,
by making it optional to mark the netID indicator (which is mandatory in case of
BOM operation scrap).
If component scrap is entered and netID is marked - then
the behavior is exactly similar to that of BOM op scrap (3.1)
If component scrap
is entered but netID is NOT marked - then the scrap adds on top of the assembly
scrap - instead of overriding.
This field becomes meaningful in cases where the
process is driven by assembly scrap (1) and routing operation scrap (2) but a
certain component by nature needs to be planned for more scrapping in excess upfront.
In our current example, as the scrap rates we enter in BOM should be to plan less than what assembly scrap refers to, the "add on top of" scrap is not applicable in concept. And to avoid the risk of not marking the netID indicator (which could lead to added up plan quantity instead of overriding with a lower value) - this field is not recommended to be used.
4) How to estimate the cost of the product accurately with different components and operation throughput rates
With all these parameters in place, the cost estimate will compute as follows
for a costing lot size of 72
component1 - 100 EA (based on assembly scrap (1)
component2 - 90 EA (based on BOM op scrap (3.1)
component3 - 72 EA (based on BOM op scrap (3.1)
operation1 - 100 EA for activity pricing based on order start
quantity (1)
operation2 - 90 EA for activity pricing based on operation1
routing scrap (2)
operation3 - 72 EA for activity pricing based on operation2
routing scrap (2)
In a nutshell,
Component quantities are driven by either BOM operation scrap (3.1), Component scrap (3.2) both of which can override or add on top of the Assembly scrap specified for the header material. Routing operation scrap if specified can override the original operation quantities driven by Assembly scrap again.
5) Actual Execution
The production scheduling profile of the header material has a setting to
re-compute actual quantities when completion confirmations are for various
operations. If this setting (checkbox) is turned off, then the initial
quantities in the order computed on the basis of (1), (2), (3) do not change
when the actual confirmation is posted for higher or lower quantities. While
this is a simpler setting to understand, the result is not desirable as we would want to readjust component quantities based on progressive execution especially for orders
that span across multiple days or even weeks.
As an example, Instead of yield of 90 on the first operation if we post a yield of only 75 - then whether to re-compute the component quantities based on that or not, is influenced by this checkbox.
The recomputation logic is quite complex, with end users sometimes unable to explain the results, especially if the settings are not made consistently between (1), (2) an d (3) above. For example, if assembly scrap (1) and BOM operation scrap (3) are entered in master data but not Routing scrap (2) is setup.
In this case,
order starts with 100 EA - so
order starts with 100 EA - so
component1 reservation quantity will be computed 100 EA
component2 is computed to 90EA based on 20% BOM op scrap adding 18 on top of planned target 72.
operation1 is final confirmed for 75
At this stage, for component2 going into operation2 the reservation quantity is recomputed (assuming profile configuration is active)
= 75 * 72/100 + 20% = 65 EA (because actual projected according to expected yield)
As this component is needed 1:1 for the product, it will be counter intuitive to say 65 needed when 75 EA of product is passed through to the operation2. This effect becomes more pronounced with more operations and each of the component having its own scrap rate overriding in the BOMs. Suffice to say that with this checkbox on. Therefore it is very important to start with the right and compatible master data in the first place.
component2 is computed to 90EA based on 20% BOM op scrap adding 18 on top of planned target 72.
operation1 is final confirmed for 75
At this stage, for component2 going into operation2 the reservation quantity is recomputed (assuming profile configuration is active)
= 75 * 72/100 + 20% = 65 EA (because actual projected according to expected yield)
As this component is needed 1:1 for the product, it will be counter intuitive to say 65 needed when 75 EA of product is passed through to the operation2. This effect becomes more pronounced with more operations and each of the component having its own scrap rate overriding in the BOMs. Suffice to say that with this checkbox on. Therefore it is very important to start with the right and compatible master data in the first place.